<?xml version="1.0" encoding="UTF-8"?>
<rss version="2.0"
	xmlns:content="http://purl.org/rss/1.0/modules/content/"
	xmlns:wfw="http://wellformedweb.org/CommentAPI/"
	xmlns:dc="http://purl.org/dc/elements/1.1/"
	xmlns:atom="http://www.w3.org/2005/Atom"
	xmlns:sy="http://purl.org/rss/1.0/modules/syndication/"
	xmlns:slash="http://purl.org/rss/1.0/modules/slash/"
	>

<channel>
	<title>Proje Yonetimi - MS Project  - PMP - PMBOK &#187; pert</title>
	<atom:link href="http://www.gokremtekir.com/index.php/tag/pert/feed/" rel="self" type="application/rss+xml" />
	<link>http://www.gokremtekir.com</link>
	<description>&#34;Hayatimiz Proje...&#34;</description>
	<lastBuildDate>Sun, 05 Feb 2012 14:17:26 +0000</lastBuildDate>
	<language>en</language>
	<sy:updatePeriod>hourly</sy:updatePeriod>
	<sy:updateFrequency>1</sy:updateFrequency>
	<generator>http://wordpress.org/?v=3.3.1</generator>
		<item>
		<title>MS Project&#8217;te LAG ve LEAD Time</title>
		<link>http://www.gokremtekir.com/index.php/2009/03/30/ms-projectte-lag-ve-lead-time/</link>
		<comments>http://www.gokremtekir.com/index.php/2009/03/30/ms-projectte-lag-ve-lead-time/#comments</comments>
		<pubDate>Mon, 30 Mar 2009 17:43:29 +0000</pubDate>
		<dc:creator>Gokrem Tekir</dc:creator>
				<category><![CDATA[MS Project]]></category>
		<category><![CDATA[aktivite]]></category>
		<category><![CDATA[cpm]]></category>
		<category><![CDATA[kritik yol]]></category>
		<category><![CDATA[network]]></category>
		<category><![CDATA[pert]]></category>
		<category><![CDATA[sıralama]]></category>

		<guid isPermaLink="false">http://www.gokremtekir.com/?p=698</guid>
		<description><![CDATA[Proje planları hazırlanırken aktiviteler arasında sıralama yapılarak, projenin Ağ Diyagramı (Network Diagram) hazırlanır.
Eğer iki aktivite birbirine ardışık olarak bağlıysa bu Finish-to-Start ilişki ile tanımlanır. Bu sayede öncül aktivite bitmeden, ardıl aktivite başlamayacak şekilde sıralnmış olur.
Eğer iki ardışık aktivite arasında belirli bir süre beklenmesi gerekiyorsa, bu iki aktivite arasına Öteleme Zamanı (LAG Time) girmek gerekecektir. Eğer [...]
No related posts.]]></description>
			<content:encoded><![CDATA[<p>Proje planları hazırlanırken aktiviteler arasında sıralama yapılarak, projenin Ağ Diyagramı (Network Diagram) hazırlanır.</p>
<p>Eğer iki aktivite birbirine ardışık olarak bağlıysa bu Finish-to-Start ilişki ile tanımlanır. Bu sayede öncül aktivite bitmeden, ardıl aktivite başlamayacak şekilde sıralnmış olur.</p>
<p>Eğer iki ardışık aktivite arasında belirli bir süre beklenmesi gerekiyorsa, bu iki aktivite arasına Öteleme Zamanı (LAG Time) girmek gerekecektir. Eğer öncül aktivite bitmeden, ardıl aktiviteyi başlatmayı planlıyorsanız bu durumda Geri Çekme Zamanı (LEAD Time) kullanmanız gerekmektedir.</p>
<p>LAG ve LEAD Time belirli bir süre olarak verilebileceği gibi öncülün süresinin yüzdesi de referans alınabilir.</p>
<p>Örnekler aşağıdadır:</p>
<p>LAG &#8211; SABİT SÜRE</p>
<p><a href="http://www.gokremtekir.com/wp-content/uploads/2009/03/lag-time.jpg"><img class="size-full wp-image-700 alignnone" title="lag-time" src="http://www.gokremtekir.com/wp-content/uploads/2009/03/lag-time.jpg" alt="lag-time" width="506" height="374" /></a></p>
<p>LAG - YÜZDESEL SÜRE  </p>
<p><a href="http://www.gokremtekir.com/wp-content/uploads/2009/03/lag-percantage.jpg"><img class="size-full wp-image-701 alignnone" title="lag-percantage" src="http://www.gokremtekir.com/wp-content/uploads/2009/03/lag-percantage.jpg" alt="lag-percantage" width="484" height="221" /></a></p>
<p> LEAD &#8211; SABİT SÜRE</p>
<p><a href="http://www.gokremtekir.com/wp-content/uploads/2009/03/lead-time.jpg"><img class="size-full wp-image-702 alignnone" title="lead-time" src="http://www.gokremtekir.com/wp-content/uploads/2009/03/lead-time.jpg" alt="lead-time" width="526" height="371" /></a></p>
<p> LEAD &#8211; YÜZDESEL SÜRE</p>
<p><a href="http://www.gokremtekir.com/wp-content/uploads/2009/03/lead-percentage.jpg"><img class="size-full wp-image-703 alignnone" title="lead-percentage" src="http://www.gokremtekir.com/wp-content/uploads/2009/03/lead-percentage.jpg" alt="lead-percentage" width="489" height="216" /></a></p>
<p>No related posts.</p>]]></content:encoded>
			<wfw:commentRss>http://www.gokremtekir.com/index.php/2009/03/30/ms-projectte-lag-ve-lead-time/feed/</wfw:commentRss>
		<slash:comments>0</slash:comments>
		</item>
		<item>
		<title>MS Project ile Üç Nokta Tahmini</title>
		<link>http://www.gokremtekir.com/index.php/2009/02/18/ms-project-ile-uc-nokta-tahmini/</link>
		<comments>http://www.gokremtekir.com/index.php/2009/02/18/ms-project-ile-uc-nokta-tahmini/#comments</comments>
		<pubDate>Wed, 18 Feb 2009 04:12:03 +0000</pubDate>
		<dc:creator>Gokrem Tekir</dc:creator>
				<category><![CDATA[MS Project]]></category>
		<category><![CDATA[pert]]></category>
		<category><![CDATA[tahminleme]]></category>

		<guid isPermaLink="false">http://www.gokremtekir.com/?p=560</guid>
		<description><![CDATA[



Danışman olarak görev aldığım, bir proje planı geliştirme çalışmasında aktivitelerin süreleri tahminlenmesi adımına gelmiştik.
 
WBS oluşturması, aktivite tanımlaması ve hatta aktiviteler arasındaki sıralamaları oluşturma süreçlerini oldukça hızlı ilerlenmiş, 230 aktiviteli bir proje planını iki gün içinde netliğe kavuşturmuştuk. İki gün boyunca projede görev alacak birimlerin temsilcleri (5 kişilik bir ekip) planın detaylı oluşturulması için sabırla planlama [...]
No related posts.]]></description>
			<content:encoded><![CDATA[<div></div>
<div><span style="mso-ansi-language: TR" lang="TR"></span></div>
<p><span style="mso-ansi-language: TR" lang="TR"><span style="font-family: Times New Roman; font-size: small;"></p>
<p class="MsoNormal" style="margin: 0cm 0cm 0pt;"><strong style="mso-bidi-font-weight: normal;"></strong></p>
<p class="MsoNormal" style="margin: 0cm 0cm 0pt;"><span style="font-family: Verdana; mso-ansi-language: TR;" lang="TR">Danışman olarak görev aldığım, bir proje planı geliştirme çalışmasında aktivitelerin süreleri tahminlenmesi adımına gelmiştik.</span></p>
<p class="MsoNormal" style="margin: 0cm 0cm 0pt;"><span style="font-family: Verdana; mso-ansi-language: TR;" lang="TR"> </span></p>
<p class="MsoNormal" style="margin: 0cm 0cm 0pt;"><span style="font-family: Verdana; mso-ansi-language: TR;" lang="TR">WBS oluşturması, aktivite tanımlaması ve hatta aktiviteler arasındaki sıralamaları oluşturma süreçlerini oldukça hızlı ilerlenmiş, 230 aktiviteli bir proje planını iki gün içinde netliğe kavuşturmuştuk. İki gün boyunca projede görev alacak birimlerin temsilcleri (5 kişilik bir ekip) planın detaylı oluşturulması için sabırla planlama sürecine katkıda bulunmuşlardı.</span></p>
<p class="MsoNormal" style="margin: 0cm 0cm 0pt;"><span style="font-family: Verdana; mso-ansi-language: TR;" lang="TR"> </span></p>
<p class="MsoNormal" style="margin: 0cm 0cm 0pt;"><span style="font-family: Verdana; mso-ansi-language: TR;" lang="TR">Fakat süre tahminleme çalışmasına geldiğimizde daha 7. aktivitede her kafadan farklı sesler çıkmaya başlamıştı, zaman ilerliyor fakat aktivitelerin ne kadar sürede yapılacağına dair net bir tahmin geliştirilemiyordu. Verilen süre tahminleri üzerinde özellikle işi fiilen yapacaklar itiraz ediyor, riskleri de düşünerek, o aktivitelerin sürelerinin uzaması gerektiğini savunuyorlardı. Yöneticiler ise projenin süresinin uzun çıkacağından çekinerek, en kısa süreyi tahmin olarak yazmaktan yanaydı.</span></p>
<p class="MsoNormal" style="margin: 0cm 0cm 0pt;"><span style="font-family: Verdana; mso-ansi-language: TR;" lang="TR"> </span></p>
<p class="MsoNormal" style="margin: 0cm 0cm 0pt;"><span style="font-family: Verdana; mso-ansi-language: TR;" lang="TR">Yukarıdaki senaryoda herkes kendi açısından haklı gözükmekte fakat buna rağmen proje yönetimi açısından böyle bir ortam da bile ortak akıl geliştirmek mümkün. Özellikle bir işin süresi ile ilgili geçmişte deneyimler mevcutsa, bu deneyimlerden yararlanarak, yeni projelerin aktivitelerinin süreleri daha kolay ve güvenilir tahmin edilebilir.</span></p>
<p class="MsoNormal" style="margin: 0cm 0cm 0pt;"><span style="font-family: Verdana; mso-ansi-language: TR;" lang="TR"> </span></p>
<p class="MsoNormal" style="margin: 0cm 0cm 0pt;"><span style="font-family: Verdana; mso-ansi-language: TR;" lang="TR">Proje yönetiminde Üç Nokta Tahmini olarak bilinen yaklaşım geçmişteki deneyimlerin en<span style="mso-spacerun: yes;">  </span>kısa (iyimser), yaklaşık ve en uzun(kötümser) değerlerini alarak, bunlardan tek bir ortalama değer oluşturmayı hedefler.</span></p>
<p class="MsoNormal" style="margin: 0cm 0cm 0pt;"><span style="font-family: Verdana; mso-ansi-language: TR;" lang="TR"> </span></p>
<p class="MsoNormal" style="margin: 0cm 0cm 0pt;"><span style="font-family: Verdana; mso-ansi-language: TR;" lang="TR">Formülasyon açısından da oldukça kolaydır. Bir işin ortalama süresi (x)</span></p>
<p class="MsoNormal" style="margin: 0cm 0cm 0pt;"><span style="font-family: Verdana; mso-ansi-language: TR;" lang="TR"> </span></p>
<p class="MsoNormal" style="margin: 0cm 0cm 0pt;"><span style="font-family: Verdana; mso-ansi-language: TR;" lang="TR">X = (İyimser + 4*Yaklaşık + Kötümser)/6 şeklindedir. Böylece süre tahmininin içine iyimser, kötümser deneyimler de eklenmiş olur.</span></p>
<p class="MsoNormal" style="margin: 0cm 0cm 0pt;"><span style="font-family: Verdana; mso-ansi-language: TR;" lang="TR"> </span></p>
<p class="MsoNormal" style="margin: 0cm 0cm 0pt;"><span style="font-family: Verdana; mso-ansi-language: TR;" lang="TR">MS Project’te bu verileri girmek için öncelikle Araç Çubuklarının arasına PERT Analysis araç çubuğunu eklemek gerkmektedir.</span></p>
<p> </p>
<p></span></span><span style="mso-ansi-language: TR" lang="TR"><span style="font-size: small;"><span style="font-family: Times New Roman;"><span style="mso-spacerun: yes"> </span> <span style="mso-ansi-language: TR" lang="TR"><span style="font-size: small;"><span style="font-family: Times New Roman;"><a href="http://www.gokremtekir.com/wp-content/uploads/2009/02/menu1.jpg"><img class="size-full wp-image-563 alignnone" title="menu1" src="http://www.gokremtekir.com/wp-content/uploads/2009/02/menu1.jpg" alt="menu1" width="124" height="250" /></a></span></span></span></span></span></span></p>
<p class="MsoNormal" style="MARGIN: 0cm 0cm 0pt"><span style="mso-ansi-language: TR" lang="TR"><span style="font-family: Times New Roman; font-size: small;"> </span></span><span style="mso-ansi-language: TR" lang="TR"><span style="font-family: Times New Roman; font-size: small;"><span style="font-family: Verdana; mso-ansi-language: TR;" lang="TR">PERT Analysis araç çubuğu aşağıdaki gibidir.</span></span></span><span style="mso-ansi-language: TR" lang="TR"><span style="font-family: Times New Roman; font-size: small;"><span style="mso-ansi-language: TR" lang="TR"><span style="font-size: small;"><span style="font-family: Times New Roman;"><a href="http://www.gokremtekir.com/wp-content/uploads/2009/02/menu2.jpg"><img class="alignnone size-full wp-image-564" title="menu2" src="http://www.gokremtekir.com/wp-content/uploads/2009/02/menu2.jpg" alt="menu2" width="176" height="32" /></a></span></span></span></span></span></p>
<p> </p>
<p class="MsoNormal" style="MARGIN: 0cm 0cm 0pt"><span style="mso-ansi-language: TR" lang="TR"><span style="font-size: small;"><span style="font-family: Times New Roman;"><span style="font-family: Verdana; font-size: 12pt; mso-ansi-language: TR; mso-fareast-font-family: 'Times New Roman'; mso-bidi-font-family: 'Times New Roman'; mso-fareast-language: EN-US; mso-bidi-language: AR-SA;" lang="TR">Yukarıdaki araç çubuğunun en sağında yer alan PERT Enty Sheet butonuna tıklanır. Karşınıza yeni bir tablo açılacaktır. </span></span></span></span></p>
<p class="MsoNormal" style="MARGIN: 0cm 0cm 0pt"><span style="mso-ansi-language: TR" lang="TR"><span style="font-family: Times New Roman; font-size: small;"> </span></span></p>
<p class="MsoNormal" style="MARGIN: 0cm 0cm 0pt"> <a href="http://www.gokremtekir.com/wp-content/uploads/2009/02/menu3.jpg"><img class="alignnone size-full wp-image-565" title="menu3" src="http://www.gokremtekir.com/wp-content/uploads/2009/02/menu3.jpg" alt="menu3" width="343" height="218" /></a></p>
<p class="MsoNormal" style="MARGIN: 0cm 0cm 0pt"><span style="mso-ansi-language: TR" lang="TR"><span style="font-family: Times New Roman; font-size: small;"> </span></span></p>
<p class="MsoNormal" style="MARGIN: 0cm 0cm 0pt"><span style="mso-ansi-language: TR" lang="TR"><span style="font-size: small;"><span style="font-family: Times New Roman;"><span style="font-family: Verdana; font-size: 12pt; mso-ansi-language: TR; mso-fareast-font-family: 'Times New Roman'; mso-bidi-font-family: 'Times New Roman'; mso-fareast-language: EN-US; mso-bidi-language: AR-SA;" lang="TR">Yazılı olan aktivite için iyimser, yaklaşık ve kötümser süre değerlerini ilgili kolonlara girmek gerekir.</span></span></span></span></p>
<p class="MsoNormal" style="MARGIN: 0cm 0cm 0pt"><span style="mso-ansi-language: TR" lang="TR"><span style="font-family: Times New Roman; font-size: small;"> </span></span></p>
<p class="MsoNormal" style="MARGIN: 0cm 0cm 0pt"><a href="http://www.gokremtekir.com/wp-content/uploads/2009/02/menu4.jpg"><img class="alignnone size-full wp-image-566" title="menu4" src="http://www.gokremtekir.com/wp-content/uploads/2009/02/menu4.jpg" alt="menu4" width="552" height="148" /></a></p>
<p class="MsoNormal" style="MARGIN: 0cm 0cm 0pt"><span style="mso-ansi-language: TR" lang="TR"><span style="font-family: Times New Roman; font-size: small;"> </span></span></p>
<div></div>
<div><span style="mso-ansi-language: TR" lang="TR"></span></div>
<div><span style="mso-ansi-language: TR" lang="TR"><span style="font-size: small;"></span></span></div>
<p><span style="mso-ansi-language: TR" lang="TR"><span style="font-size: small;"><span style="font-family: Times New Roman;"></p>
<p class="MsoNormal" style="margin: 0cm 0cm 0pt;"><span style="font-family: Verdana; mso-ansi-language: TR;" lang="TR">Yukarıdaki verilerin ilgili formülle hesaplanması için PERT <span style="font-size: small;"><span style="font-family: Times New Roman;"><span style="mso-spacerun: yes"><a href="http://www.gokremtekir.com/wp-content/uploads/2009/02/menu5.jpg"><img class="size-full wp-image-567 alignleft" title="menu5" src="http://www.gokremtekir.com/wp-content/uploads/2009/02/menu5.jpg" alt="menu5" width="24" height="22" /></a></span></span></span>Analysis araç çubuğunun içinde <span style="mso-spacerun: yes;"> </span>(Calculate PERT) butonuna bir kez basılır ve aşağıdaki uyarı ile karşılaşılır. </span></p>
<p></span></span></span></p>
<p class="MsoNormal" style="MARGIN: 0cm 0cm 0pt"><a href="http://www.gokremtekir.com/wp-content/uploads/2009/02/menu6.jpg"><img class="alignnone size-full wp-image-562" title="menu6" src="http://www.gokremtekir.com/wp-content/uploads/2009/02/menu6.jpg" alt="menu6" width="543" height="99" /></a> </p>
<p class="MsoNormal" style="MARGIN: 0cm 0cm 0pt"><span style="mso-ansi-language: TR" lang="TR"><span style="font-family: Times New Roman; font-size: small;"> </span></span></p>
<div></div>
<div><span style="mso-ansi-language: TR" lang="TR"></span></div>
<div><span style="mso-ansi-language: TR" lang="TR"><span style="font-size: small;"></span></span></div>
<p><span style="mso-ansi-language: TR" lang="TR"><span style="font-size: small;"><span style="font-family: Times New Roman;"></p>
<p class="MsoNormal" style="margin: 0cm 0cm 0pt;"><span style="font-family: Verdana; mso-ansi-language: TR;" lang="TR">Bu uyarıya da Yes denildikten sonra aktivitenin süre kolonu verilen üç değere göre hesaplandığı görülür.</span></p>
<p class="MsoNormal" style="margin: 0cm 0cm 0pt;"> </p>
<p class="MsoNormal" style="margin: 0cm 0cm 0pt;"><span style="font-family: Verdana; mso-ansi-language: TR;" lang="TR">İşte yukarıdaki adımları gerçekleştirerek, bütün proje taraflarını memnun edecek bir yöntemle aktivite süre tahminlerini gerçekleştirdik. Böyle bir uygulamaya kimse itiraz etmedi.</span></p>
<p></span></span></span></p>
<p>No related posts.</p>]]></content:encoded>